Tasks and periodic checks on the outside of the boiler. All the doors of access and work areas must be treated with airtight gasket 362 is effective to use. Chimney system must have a connection that effectively closed and if necessary isolated.

Shell boilers and parts thereof should be well insulated and must ensure that the insulation is sufficient. If insulation is used in boilers, pipes and hot water cylinder installed several years ago, almost certainly the insulation is thin, although apparently in good condition. Keep in mind that insulation is installed when the fuel cost is very low. The addition would be better thickness.

At the end of warm-up time / use, during the summer, the boiler must be fully closed and fully covered the surface of the plate with dessicant inserts. (Only applicable to boilers that are not operated between the heating time / usage.)

Increasing steam and hot water boilers.

Dirt in the boiler water that collects in the boiler, has a concentration limit depends on the type and boiler load. Boiler blow down should be minimized, but the density of water provision should be maintained. Heat from blow down water should be used.

In steam boilers, water treatment is sufficient to prevent the formation of foaming (the formation of foam / froth) or priming and consequently carry the excess water and chemicals into the steam system? For the steam boiler, whether the automatic control of the water surface to work? The existence of interconnection pipes can be very dangerous. Is pengecekkan has done regularly for air leaks around the boiler, door or between the boiler and chimney? The former will reduce the efficiency, the latter can reduce the quality of steam and drought led to condensation, corrosion, and Smutting.

required ratio of fuel / air is set. Detector and the existing control equipment should be labeled and checked periodically. Display lock should have a manual tuner and alarm. Testing should be done, or installation of permanent indicators for monitoring the condition of burner pressure conditions / operating temperature.

In the boiler fuel oil or gas, the system wires to disable links fussible / shutdown if there is a fire or overheating across the street through which employees, must be placed in a position above his head. Emergency shutdown facility located at the exit boiler room.

Tasks and periodic checks on the outside of the boiler. All the doors of access and work areas must be treated with airtight gasket 362 is effective to use. Chimney system must have a connection that effectively closed and if necessary isolated.

Shell boilers and parts thereof should be well insulated and must ensure that the insulation is sufficient. If insulation is used in boilers, pipes and hot water cylinder installed several years ago, almost certainly the insulation is thin, although apparently in good condition. Keep in mind that insulation is installed when the fuel cost is very low. The addition would be better thickness.

At the end of warm-up time / use, during the summer, the boiler must be fully closed and fully covered the surface of the plate with dessicant inserts. (Only applicable to boilers that are not operated between the heating time / usage.)

Increasing steam and hot water boilers.

Dirt in the boiler water that collects in the boiler, has a concentration limit depends on the type and boiler load. Boiler blow down should be minimized, but the density of water provision should be maintained. Heat from blow down water should be used.

In steam boilers, water treatment is sufficient to prevent the formation of foaming (the formation of foam / froth) or priming and consequently carry the excess water and chemicals into the steam system? For the steam boiler, whether the automatic control of the water surface to work? The existence of interconnection pipes can be very dangerous. Is pengecekkan has done regularly for air leaks around the boiler, door or between the boiler and chimney? The former will reduce the efficiency, the latter can reduce the quality of steam and drought led to condensation, corrosion, and Smutting.

required ratio of fuel / air is set. Detector and the existing control equipment should be labeled and checked periodically. Display lock should have a manual tuner and alarm. Testing should be done, or installation of permanent indicators for monitoring the condition of burner pressure conditions / operating temperature.

In the boiler fuel oil or gas, the system wires to disable links fussible / shutdown if there is a fire or overheating across the street through which employees, must be placed in a position above his head. Emergency shutdown facility located at the exit boiler room.

0 comments :

Post a Comment

you give times, i give you world,
if you have a website or something, please at the contents. thanks..

best regards,

Share |
Blog Advertising
Get paid To Promote at any Location